On 30 October, South Korea’s Ministry of Climate, Energy and Environment officially announced the launch of its competitive tender for fixed-price offshore wind power contracts for the second half of 2026. The tender covers a total installed capacity of approximately 2.2 GW. Coupled with the 1.8 GW already awarded in the first half of the year, South Korea’s total offshore wind tender volume for 2026 will reach around 4 GW, setting a new annual record in the country.
This round marks the first bidding exercise since South Korea released its Medium- and Long-Term Offshore Wind Tender Roadmap in June 2026, and the first time the country has raised its annual tender scale to 4 GW. Under the roadmap, South Korea targets a cumulative tendered offshore wind capacity of 55 GW by 2035, with annual tender volume steadily staying above 4 GW. The stable market outlook is designed to unlock economies of scale and drive a continuous decline in the levelized cost of electricity (LCOE).
In terms of technology mix, the 2.2 GW H2 tender comprises 1,700 MW of fixed-bottom offshore wind and 500 MW of floating offshore wind. The fixed-bottom segment is further split into a 1,400 MW general track and a 300 MW public-led track. The public-led track requires shareholding by public institutions, balancing project delivery efficiency with public benefits.
On price caps, this tender maintains a cost-reduction orientation. For onshore-grid-connected fixed-bottom projects, the price cap is set at 168,937 KRW per MWh (approximately CNY 0.84 per kWh), while the cap for Jeju Island fixed-bottom projects stands at 168,913 KRW per MWh. For floating projects, the corresponding price caps are 174,003 KRW per MWh (approximately CNY 0.87 per kWh) and 173,979 KRW per MWh respectively. Compared with the H1 tender, the price cap for fixed-bottom projects has been cut by 1.34%, and that for floating projects by 0.63%, aligning with South Korea’s long-term target of bringing LCOE below 250 KRW per kWh by 2030 and below 150 KRW per kWh by 2035.
In terms of evaluation rules, this tender does not award contracts solely on the lowest bid. A range of non-price criteria will be comprehensively assessed, including community acceptance, industrial and economic contribution, domestic supply chain development, operation and maintenance (O&M) capability, safety and resilience, and grid connection performance. The mechanism guides projects to balance economic viability with industrial spillover value, improve the domestic offshore wind supporting ecosystem, and support the commercial deployment of 20 MW-class domestically manufactured wind turbines by 2034.
Tender award results are expected to be announced to bidders on a rolling basis starting from December.